  • Slab prepped and poured!

    Slab prepped and poured!

    The slab has been poured, and we’re ready to frame! First, the foundation fill needed to be leveled and compacted, vapor barrier laid down, insulation…

  • Foundation work continues…

    Foundation work continues…

    The forms were removed and several layers of waterproofing tar applied. Miradrain, an additional waterproofing drainboard, was nailed onto the foundation walls. The perf pipe…

  • Lot #10 has closed!

    Lot #10 has closed!

    From a construction site to a home! On July 31st, the house we built on Lot #10 sold to an income-qualified, local, workforce family. We…

  • The final details…

    The final details…

    With all the front exterior painting done, we could finally install the porch roof! Then we finished all the window and door trim. A big…