East deck!
While the rest of the framing and roof work was happening, we were also building the very sturdy east deck! First the support framing… then…
-
Metal roof is on!
The rains cleared and Christian and Talen installed the metal roof, with ground support from Blake, on Oct 27 and 28th! Another milestone!
-
Framing and strapping!
While work was happening on the roof and the east deck, great progress was made on the framing and the strapping. Framing the stairs, the…
-
Trusses and Roof!
On October 1st, the trusses, the trusses were delivered. Then, starting on October 6, we had a big week culminating in the roof being finished!…