  • Prepping the Trim

    Prepping the Trim

    While the subcontractors have been busy at the house, Richard Epstein and his crew of finish carpenters have been prepping the trim. Big thanks to…

  • Drywall installed!

    Drywall installed!

    Another milestone and now the drywall is installed!

  • Insulation installed!

    Insulation installed!

    We passed the plumbing and mechanical inspection on April 2, and the insulation subcontractor, A & E Insulation, was able to start right away! The…

  • Power and water now connected!

    Power and water now connected!

    The milestones are now being accomplished in rapid succession! Water was connected on March 23rd! Then we passed the LNI inspection and on March 27,…